News
Is Red Deer Over 100,000 Residents? Depends If You Ask Ottawa or Edmonton!
According to the federal government Red Deer’s population is 100,418. As far as the federal government is concerned that will be Red Deer’s population until the results of the next federal census are released in 2021.
But provincially, Red Deer’s population is a different matter. The Province of Alberta refers to data supplied by the latest “municipal” census. The City of Red Deer’s 2016 census appears in hindsight to have been done at perhaps the lowest point in our recession. The last municipal census showed Red Deer’s population had actually shrunk from a high of 100,807 in 2015, to 99,832 last year. That lower figure of just ‘under’ 100,000 is the one the province will use to set funding for The City of Red Deer, until our next census is held.
This all leaves City Council in a bit of a tough spot. Budget deliberations just wrapped up and council decided not to fund a census in 2017.
So which figure should we refer to? Mayor Tara Veer says we should be very confident in using the 2016 “federal” census which shows Red Deer’s population is 100,418. Until Red Deer completes another municipal census, the federal census is the latest information available.
Alberta
Regulator rules in favour of Trans Mountain route deviation

Workers place pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023. THE CANADIAN PRESS/Darryl Dyck
By Amanda Stephenson in Calgary
The Canada Energy Regulator has approved Trans Mountain Corp.’s application to modify the pipeline’s route, a decision that could spare the government-owned pipeline project from an additional nine-month delay.
The regulator made the ruling Tuesday, just one week after hearing oral arguments from Trans Mountain and a B.C. First Nation that opposes the route change.
It didn’t release the reasons for its decision Tuesday, saying those will be publicized in the coming weeks.
By siding with Trans Mountain Corp., the regulator is allowing the pipeline company to alter the route slightly for a 1.3-kilometre stretch of pipe in the Jacko Lake area near Kamloops, B.C., as well as the construction method for that section.
Trans Mountain Corp. had said it ran into engineering difficulties in the area related to the construction of a tunnel, and warned that sticking to the original route could result in up to a nine-month delay in the pipeline’s completion, as well as an additional $86 million more in project costs.
Trans Mountain has been hoping to have the pipeline completed by early 2024.
But Trans Mountain’s application was opposed by the Stk’emlúpsemc te Secwépemc Nation, whose traditional territory the pipeline crosses and who had only agreed to the originally proposed route.
In their regulatory filing, the First Nation stated the area has “profound spiritual and cultural significance” to their people, and that they only consented to the pipeline’s construction with the understanding that Trans Mountain would minimize surface disturbances by implementing specific trenchless construction methods.
The Stk’emlúpsemc te Secwépemc argued that Trans Mountain never said its originally proposed construction method was impossible, only that it couldn’t be done in time to meet a Jan. 1 in-service date for the pipeline.
The First Nation didn’t respond to a request for comment by publication time.
The Trans Mountain pipeline is Canada’s only pipeline system transporting oil from Alberta to the West Coast. Its expansion, which is currently underway, will boost the pipeline’s capacity to 890,000 barrels per day (bpd) from 300,000 bpd currently.
The pipeline — which was bought by the federal government for $4.5 billion in 2018 after previous owner Kinder Morgan Canada Inc. threatened to scrap the pipeline’s planned expansion project in the face of environmentalist opposition and regulatory hurdles — has already been plagued by construction-related challenges and delays.
Its projected price tag has since spiralled: first to $12.6 billion, then to $21.4 billion and most recently to $30.9 billion (the most recent capital cost estimate, as of March of this year).
Keith Stewart with Greenpeace Canada said it’s alarming to see the regulator over-rule the wishes of Indigenous people in order to complete a pipeline on deadline.
“Every Canadian should be outraged that our public regulator is allowing a publicly owned pipeline to break a promise to Indigenous people to protect lands of spiritual and cultural significance,” Stewart said.
The federal government has already approved a total of $13 billion in loan guarantees to help Trans Mountain secure the financing to cover the cost overruns.
Trans Mountain Corp. has blamed its budget problems on a variety of factors, including inflation, COVID-19, labour and supply chain challenges, flooding in B.C. and unexpected major archeological discoveries along the route.
Given the Canadian regulatory system has a reputation for being slow and cumbersome, it was surprising to see the Canada Energy Regulator rule so quickly on Trans Mountain’s route deviation request, said Richard Masson, executive fellow with the University of Calgary’s School of Public Policy.
“It’s a challenging decision to have to make, when you’ve got a $30 billion pipeline that needs to be completed,” Masson said.
“If there’s no feasible way to do that tunnel, then I guess you have to allow for this.”
Masson added that if the regulator had denied Trans Mountain’s request, it would have been bad news for taxpayers as well as the federal government, which is seeking to divest the pipeline and has already entered into negotiations with several interested Indigenous-led buyers.
It also would have been bad news for Canadian oil companies, who have been eagerly anticipating the pipeline’s start date to begin shipping barrels to customers.
“If this can result in the pipeline being completed by year-end and started up in the first quarter, that’s good news. The world is still looking for oil, and oil prices are up at US$90 a barrel,” Masson said.
This report by The Canadian Press was first published Sept. 25, 2023.
Disaster
CP NewsAlert: Quebec police say three fishers are dead after boat sinks
MONTREAL — Quebec provincial police say three people are dead after a fishing boat sunk off the province’s Lower North Shore.
Police say six people were aboard the boat out of Blanc Sablon, Que., when it ran into trouble around midnight.
More coming.
The Canadian Press
-
Dr John Campbell10 hours ago
Excess deaths in Canada and most western nations remain very high long after pandemic deaths subside
-
Crime8 hours ago
Parole board warned employees about threats following Saskatchewan stabbings: emails
-
Justice2 days ago
Man charged with first degree murder in shooting death of B.C. RCMP officer
-
Business2 days ago
Moneris confirms credit and debit card processing outage, but offers few details
-
Alberta1 day ago
Hot rental market makes search ‘stressful’ for many ā and it won’t get better soon
-
Automotive1 day ago
Ford workers in Canada ratify agreement, set precedent for other automakers
-
conflict8 hours ago
NDP House leader says Speaker should resign after honouring man who fought for Nazis
-
National8 hours ago
Jewish group demands apology after MPs honoured man who fought for Nazis