Connect with us
[the_ad id="89560"]

News

Regional Wastewater Line On Budget and On Time

Published

on

North Red Deer Regional Wastewater System Construction Update from The City of Lacombe

The North Red Deer Regional Wastewater Services Commission (NRDRWWSC) is pleased to report that construction on the wastewater transmission system connecting Lacombe, Blackfalds and Lacombe County to the regional wastewater treatment facility in Red Deer is on budget and progressing well.

Six construction contracts are underway concurrently:

  1. Pipeline construction from the Odour Management Facility to the City of Red Deer’s Wastewater treatment Plant is expected to be completed ahead of schedule in November 2017. PVC installation was completed by mid-October, and the entrance chamber construction is on-going and nearly complete. (see Fig. 1: Installation of PVC gravity pipe. Trench box being utilized due to poor ground conditions.)
  2. Construction of the Odour Management Facility is on track for completion on schedule by mid-January 2018. Precast concrete walls are up and work on the building roof is ongoing. (see Fig. 2: Construction of the Odour Management Facility.)
  3. Construction on the pipeline from Blackfalds to the Odour Management Facility is on schedule. Crews are currently installing pipe North of Highway 597, including well point dewatering. Pressure testing completion is set for December 15, 2017. (see Fig. 3: Installation of a case bore on the North side of Blindman River.)
  4. Construction of the Blackfalds Lift Station is on schedule for completion in late January 2018. PVC site piping is being completed and the precast concrete walls are up and roof work is ongoing. (see Fig. 4: Construction of the Blackfalds Lift Station.)
  5. Pipeline construction from Lacombe to Blackfalds, is ahead of schedule. Crews are working on pipe installation towards Lacombe (Range Road 264) and along Highway 597. Pressure testing completion is set for December 15, 2017. (see Fig. 5: Pipe installation within a trenched area.)
  6. Construction of the Lacombe Lift Station is on schedule for completion in late February 2018. All cast-in-place concrete work has been completed and all underground pipe and backfilling to grade level has been completed. (see Fig. 6: Construction progress of the Lacombe Lift Station.)

Construction completion of the overall project is scheduled for March 31, 2018.

The project is expected to cost approximately $71 million.

Funding partners for the project include the Government of Canada, the Alberta Government and the NRDRWWSC municipal partners (City of Lacombe, Town of Blackfalds, and Lacombe County) as well as the City of Red Deer.

For more information, please visit http://www.nrdrwwsc.ca.

Fig 1 Fig 2 Fig 3 Fig 4 Fig 5 Fig 6
<
>
Pipeline between Blackfalds and Odour Management Facility

COMMUNITY CALENDAR

february, 2018

wed14feb - 4aprfeb 146:00 pmapr 4TRIPLE T -Act/Dance/SingYouth 6 Create Your Own Play!6:00 pm - (april 4) 7:45 pm

thu15feb - 5aprfeb 155:30 pmapr 5Art of Friendship5:30 pm - (april 5) 7:30 pm

mon19feb9:00 am- 5:00 pmServus Family Day Fun9:00 am - 5:00 pm

mon19feb11:00 am- 4:00 pmFamily Day11:00 am - 4:00 pm

tue20feb6:00 pm- 8:00 pmCaregiver Connections6:00 pm - 8:00 pm MST CMHA Learning Annex, First Red Deer Place 4911 - 51 Street, Suite 400 Red Deer, AB T4N 6V4

wed21feb - 25All DayThe 2018 Red Deer Gem & Mineral Show(All Day)

thu22feb7:00 pm- 10:00 pmPaint Night7:00 pm - 10:00 pm

fri23feb - 25All Day2018 Central Alberta Film Festival(All Day)

sat24feb11:00 am- 2:00 pmInternational Mother Language Day Event11:00 am - 2:00 pm

sun25feb8:30 am- 3:00 pmRBC Training Ground QualifierCOULD IT BE YOU?8:30 am - 3:00 pm

X