The Runaway Costs of Government Construction Projects

Published

13 minute read

From the C2C Journal

By Gwyn Morgan

Ottawa’s post-pandemic $300 billion spending orgy was coupled with the pompous claim to “Build Back Better”. As it happened, most of that spending was recklessly borrowed – stoking inflation – while Build Back Better was a dud, was discarded in embarrassment and, if recalled at all today, is told as a sick joke. Far too many planned projects now sink into a quicksand of political haggling, regulatory overkill, mission creep, design complexity and, if built at all, bungled execution. Looking at specific examples, Gwyn Morgan presents the lamentable results: far less is actually getting built across Canada, nearly everything takes forever and – worst of all – costs routinely soar to ludicrous levels. Added to that, Morgan notes, are woke-based criteria being imposed by the Trudeau government that are worsening the vicious cycle.

Not so long ago, a $10 million government infrastructure project was regarded as a significant expenditure. Nowadays, $10 million doesn’t come close to funding projects as simple as a firehall or new police station. Here in the Victoria region, a new firehall in the District of Saanich, originally budgeted at $25.6 million, has jumped to nearly $45 million over four years – and construction has barely begun. The facility will support 10 firefighters. In the Langford District, the estimated cost of a new RCMP building is an incomprehensible $82 million – and of course, nothing has actually been done yet, so this price tag will surely soar. Just north of Victoria, the cost of what was to be a simple flyover eliminating a dangerous left turn across the busy Patricia Bay Highway has spiked from its original estimate of $44 million to $77 million.

These cost increases seem big to us here on “Fantasy Island”, but they would amount to a rounding error in mega-city Toronto. The Ontario Line, a 15.6-kilometre light-rail transit line connecting the Science Centre to Ontario Place, was budgeted at $10.9 billion when first announced in 2019. A series of updates have seen the cost balloon to an estimated $19 billion – an increase of more than 70 percent – with the completion date pushed out by four years to 2031. Expect more cost increases to be announced.

These are just a few examples of municipal and provincial cost increases and overruns. The story is similar from coast to coast, with no project type or size in any municipality or province immune to an unsettling syndrome that seems to prevent nearly anything from being planned cost-effectively and then delivered on budget. Obviously, the total for all such projects planned or underway across Canada is immensely higher – surely in the tens of billions of dollars.

Mismanagement syndrome: From simple firehalls to subway sections to straightforward software, governments at all levels have lost control of costs. Replacing a small firehall in Saanich on Vancouver Island (top left and top right) will cost nearly $2,000 per square foot or $4.5 million per firefighter; the pricetag for Toronto’s planned Ontario Line (bottom left) has zoomed from $10.9 billion to $19 billion; and the notorious ArriveCAN (bottom right) consumed $54 million to deliver an $80,000 software tool. (Sources of images: (top left) District of Saanich; (top right) rendering courtesy of hcma, retrieved from naturally:wood; (bottom left) Metrolinx; (bottom right) WestJet/Facebook)

Now for the project mismanagement champion of all. Statistics Canada data show that federal capital infrastructure project expenditures totalled $24.1 billion in the period 2018-2021 (the most recent year for which figures are available). Given that Ottawa bureaucrats are famous for mismanaging virtually every project (think of the notorious ArriveCAN app, whose development blew through $54 million to yield a buggy software tool that private-sector geeks could have cranked out for $80,000), there can be no doubt that a lot of those billions were to pay for overruns resulting from a combination of sloppy design specifications and poor execution.

But now the Trudeau government has added costly “social justice” specifications to federal procurement requirements, including participation by ethnic minorities, disabled persons and diverse genders, plus other elements of woke ideology. These elements were clearly demonstrated in what I’ll call “The Great Helicopter Hangar Saga”. The following is a recollection from sources I know to be completely reliable.

The Canadian Forces’ 443 (Pacific) Maritime Helicopter Squadron’s hangar had been located adjacent to the Victoria Airport for many years. In November 2004, the Department of National Defence (DND) announced the award of a $1.8 billion contract for 28 Sikorsky CH-148 Cyclone helicopters, of which a number were to be based on Vancouver Island. A new hangar was required, which seems reasonable. DND engineers designed a facility that would meet the squadron’s needs at an estimated cost of roughly $18 million. Then they handed the project to Public Works and Government Services Canada. That’s when the project entered an ephemeral space resembling the old sci-fi TV series The Twilight Zone.

Public Works decided the hangar needed to be able to “sustain operations” in the event of a magnitude 8.0 earthquake – an incomprehensible decision for several reasons. First, 8.0 on the Richter Scale is seven times larger than the most severe earthquake ever recorded on Vancouver Island. Second, the severity of earthquake damage at any given location depends on its subsurface. Buildings sitting on soil and gravel suffer much more damage than those built on bedrock because the soft material changes from behaving like a solid to behaving like a thick liquid, amplifying the ground’s shaking. The Pacific Maritime Helicopter Squadron’s hangar was located on solid bedrock. That alone made it highly earthquake-resilient.

But the Public Works technocrats were oblivious to those facts, or didn’t care. Instead, their design demanded steel piles driven into the bedrock at a cost of $8 million. That alone reportedly delayed the project by two years. Cross-bracing of the interior wall openings added more millions. When construction of the actual building finally began, government bureaucrats specified more office space, locker and “administrative security” facilities than what the DND had considered necessary, adding more costs.

Then came the woke-related costs. In determining the contract award, Public Works required First Nations involvement both as subcontractors and in the workforce, extensive gender diversity and complete disabled access. Elevators were ordered equipped with Braille at the control buttons plus voice recognition – along with full wheelchair accessibility. Members of the military joked that all these extras must be for the “blind and disabled pilots”. By the time the new hangar was handed back to the military, the DND’s $18 million project had skyrocketed to a staggering $155 million.

Braille for blind pilots: To base some of the Royal Canadian Air Force’s new CH-148 Cyclone maritime helicopters (above, performing in-flight refuelling with a navy frigate in the North Atlantic) on Vancouver Island, federal Public Works bureaucrats took a reasonable $18 million Department of Defence design and transformed it into a $155 million fiasco reflecting Ottawa’s diversity obsessions and wokist ideology. (Sources of photos: (top) Lockheed Martin, retrieved from Navy Recognition; (bottom) The Lookout)

In July 2019, Phillip Cross wrote an inciteful column for the Financial Post entitled, “Why governments keep screwing up major infrastructure projects”. As Cross put it, “Prominent studies of domestic and international public infrastructure projects found cost overruns averaged between 45 and 86 percent.” Why? In Cross’s view, a big part of the problem is that “public projects suffer from a lack of accountability. Governments evaluate projects not according to the performance-based criteria of the private sector, but by their conformity to rules and processes.”

Cross’s points are well-taken and illustrated by circling back to our Saanich Firehall example. The new facility’s 23,476 square feet will incur a construction cost of over $1,900 per square foot (assuming the new $45 million budget is big enough). That is six to nine times typical construction costs for commercial buildings which, as this report shows, average $200-$300 per square foot. And while a firehall may well be a bit more sophisticated and hence costly to build than, say, a retail strip mall, the Saanich firehall’s costs are also wildly out of proportion to any class of construction, as the fascinating accompanying chart shows. As you can see, it lists a range of $415-$485 per square foot for emergency services buildings. Even technology-heavy, highly customized construction categories like hospitals and data centres come in at no more than $805 and $1,055 per square foot, respectively. Clearly, something is seriously wrong in Saanich and many other locations across Canada.

Outrageous by any standard: The ballooning construction costs of recent public-sector projects are many times higher than 2022 averages for all categories – even in a high-cost market like Vancouver. (Source of graph: Statista)

This evidence of dysfunctional project mismanagement comes at a time when public infrastructure spending is at record levels, dominated by the Justin Trudeau government’s $33 billion 2023-24 infrastructure project budget and sure to be made even more dysfunctional and costly by the Liberals’ surreptitious implementation of woke ideology. When will Canadians awaken and rise up against a government that defies the values of honesty and openness our country was built on?

Gwyn Morgan is a retired business leader who was a director of five global corporations.

Source of main image showing Vancouver’s Broadway Subway project: BC Ministry of Transportation and Infrastructure; retrieved from ReNew Canada.

Todayville is a digital media and technology company. We profile unique stories and events in our community. Register and promote your community event for free.

Follow Author

Business

Carney’s Honeymoon Phase Enters a ‘Make-or-Break’ Week

Published on

From the National Citizens Coalition 

The National Citizens Coalition (NCC) is sounding the alarm on a critical week for the Carney government, which, despite enjoying an unearned honeymoon in the polls, has delivered zero results for everyday Canadians. As the G7 summit looms large and the House of Commons prepares to adjourn, this is a make-or-break moment for Prime Minister Mark Carney to prove his government is more than empty promises. Canadians are watching, and the NCC is calling out the glaring failures that threaten a grim summer of economic decline, and continued crime, chaos, and rising unemployment.

Housing Minister Gregor Robertson Caught in $10.85 Million Scandal

Recent revelations from Blacklock’s Reporter expose Housing Minister Gregor Robertson’s attempt to conceal $10.85 million in personal property investments during Commons questioning. This shocking lack of transparency from the minister tasked with addressing Canada’s housing crisis raises serious questions about his integrity and ability to prioritize Canadians struggling with skyrocketing costs. While Robertson dodges accountability, and Carney apparently scoffs at providing housing relief to millions suffering under a Liberal-made crisis, young professionals and young families are wondering if they’ll ever have a chance to own a home bigger than Canada’s much-maligned supply of ‘dog-crate condos.’

The NCC demands a full ethics investigation, the resignation of Gregor Robertson — who, as one of the architects of the Vancouver housing crisis, should have never been handed this file to begin with — and immediate action to restore trust in this critical portfolio.

Pipeline Delays and Provincial Obstruction Threaten Economic Growth

The Carney government’s inaction on pipelines is stalling Canada’s economic potential. Despite promises of “nation-building projects,” British Columbia and Quebec continue to block and veto critical energy infrastructure, with Carney failing to assert federal leadership. His vague talk of “consensus” and “decarbonized” barrels has led to zero progress, leaving Alberta’s economy in limbo and Canadians facing higher energy costs. With no clear plan to advance projects, the government is squandering opportunities to create jobs and secure energy sovereignty. The NCC urges Carney to act decisively this week to break the provincial logjam and deliver results.

Immigration Chaos: Lena Diab’s Unchecked Honour System Fails Canadians

Immigration Minister Lena Diab’s reliance on an ‘honour system’ for millions of temporary visitors with expiring visas is a recipe for disaster. As Canada grapples with unsustainable immigration levels, Diab’s apparent plan for millions of temporary workers and failed ‘diploma mill’ attendees assumes compliance without enforcement, ignoring the high-propensity for fraud, and the ongoing and urgent strain on housing, healthcare, and public services. The Liberals’ Strong Borders Act promises reform, but its loaded with unnecessary overreach and vague measures.

A lack of urgency leaves Canadians vulnerable to further crime, chaos, closed emergency rooms, high rents, and failing infrastructure. With immigration continuing to spiral out of control, the NCC calls for concrete action to drastically lower immigration targets, expedite deportations, and prioritize Canadian citizens and the record amounts of unemployed before the House adjourns.

Canadians Deserve Results, Not More Hollow “Elbows up” or “Team Canada” Rhetoric

This week’s G7 summit in Alberta and the impending House adjournment are the Carney government’s last chance to show leadership, before an undeserved summer break for a government that will be overseeing deepening economic decline, rising crime under a refusal to tackle catch-and-release bail, and growing unemployment. Canadians cannot afford another season of unfulfilled promises and unchecked crises. The NCC demands Carney use the G7 platform to secure trade stability, meaningful energy deals with our allies, and table a federal budget to address the cost-of-living crisis made worse by inflationary Liberal spending. Failure to act now will cement an early legacy of inaction and leave Canadians to endure a prolonged period of hardship.

“The Carney government’s honeymoon has been built on hype, not results,” says NCC Director Alexander Brown. “From Gregor Robertson’s hidden millions, to stalled pipelines, to an immigration system in continued disarray, Canadians — and particularly young Canadians — are being let down. This week is Carney’s chance to prove he can deliver beyond the lies that were told to placate a portion of the electorate at the polls. If he fails to act, the economic decline, the crime and chaos, will only worsen, and everyday Canadians will pay the price.

“True Canadian leaders like Alberta Premier Danielle Smith are in attendance at the G7 along with Carney. If actual acts of ‘nation-building,’ and not more net-zero de-growth, do not come naturally to the PM, he should turn to those who have never wavered in their quest to make life more affordable for the hard-working citizens they are privileged to represent, and who know when to get out of the way to allow Canadians to prosper. More of the same internal, ideological sabotage from the Liberals cannot ruin this dire moment for Canada’s rebirth and recovery.”

The NCC calls on all Canadians to hold the Carney government accountable. Join us in demanding transparency, action, and results before the House adjourns and the G7 summit concludes. Together, we can fight for a stronger, more prosperous Canada.

About the National Citizens Coalition: Founded in 1967, the NCC is a non-profit organization dedicated to advocating for individual freedom, lower taxes, less government waste, and a stronger Canada. We hold governments accountable and fight for the interests of everyday Canadians.

Continue Reading

Alberta

Alberta announces citizens will have to pay for their COVID shots

Published on

From LifeSite News

By Anthony Murdoch

The government said that it has decided to stop ‘waste’ by not making the shots free starting this fall.

Beginning this fall, COVID shots in the province will have to be pre-ordered at the full price, about $110, to receive them.  (This will roll out in four ‘phases’. In the first phases COVID shots will still be free for those with pre-existing medical conditions, people on social programs, and seniors.)

The UCP government in a press release late last week noted due to new “federal COVID-19 vaccine procurement” rules, which place provinces and territories as being responsible for purchasing the jabs for residents, it has decided to stop “waste” by not making the jab free anymore.

“Now that Alberta’s government is responsible for procuring vaccines, it’s important to better determine how many vaccines are needed to support efforts to minimize waste and control costs,” the government stated.

“This new approach will ensure Alberta’s government is able to better determine its overall COVID-19 vaccine needs in the coming years, preventing significant waste.”

The New Democratic Party (NDP) took issue with the move to stop giving out the COVID shots for free, claiming it was “cruel” and would place a “financial burden” on people wanting the shots.

NDP health critic Sarah Hoffman claimed the move by the UCP is health “privatization” and the government should promote the abortion-tainted shots instead.

The UCP said that in 2023-2024, about 54 percent of the COVID shots were wasted, with Health Minister Adriana LaGrange saying, “In previous years, we’ve seen significant vaccine wastage.”

“By shifting to a targeted approach and introducing pre-ordering, we aim to better align supply with demand – ensuring we remain fiscally responsible while continuing to protect those at highest risk,” she said.

The jabs will only be available through public health clinics, with pharmacies no longer giving them out.

The UCP also noted that is change in policy comes as a result of the Federal Drug Administration in the United States recommending the jabs be stopped for young children and pregnant women.

The opposite happened in Canada, with the nation’s National Advisory Committee on Immunization (NACI) continuing to say that pregnant women should still regularly get COVID shots as part of their regular vaccine schedule.

The change in COVID jab policy is no surprise given Smith’s opposition to mandatory shots.

As reported by LifeSiteNews, early this year, Smith’s UCP government said it would consider halting COVID vaccines for healthy children.

Smith’s reasoning was in response to the Alberta COVID-19 Pandemic Data Review Task Force’s “COVID Pandemic Response” 269-page final report. The report was commissioned by Smith last year, giving the task force a sweeping mandate to investigate her predecessor’s COVID-era mandates and policies.

The task force’s final report recommended halting “the use of COVID-19 vaccines without full disclosure of their potential risks” as well as outright ending their use “for healthy children and teenagers as other jurisdictions have done,” mentioning countries like “Denmark, Sweden, Norway, Finland, and the U.K.”

The mRNA shots have also been linked to a multitude of negative and often severe side effects in children and all have connections to cell lines derived from aborted babies.

Many Canadian doctors who spoke out against COVID mandates and the experimental mRNA injections were censured by their medical boards.

LifeSiteNews has published an extensive amount of research on the dangers of the experimental COVID mRNA jabs that include heart damage and blood clots.

Continue Reading

Trending

X