In a post on his Truth Social media platform Monday night, President Donald Trump said he still wants to see the Keystone XL pipeline through to completion. Here is the full text of the president’s post:
“Our Country’s doing really well, and today, I was just thinking, that the company building the Keystone XL Pipeline that was viciously jettisoned by the incompetent Biden administration should come back to America, and get it built — NOW! I know they were treated very badly by Sleepy Joe Biden, but the Trump Administration is very different — Easy approvals, almost immediate start! If not them, perhaps another Pipeline Company. We want the Keystone XL Pipeline built!”
For those unaware, the company that spent a decade attempting to finance, obtain permits, and build the Keystone XL pipeline project is TC Energy (formerly Trans Canada), which is headquartered in Calgary, Alberta, Canada.
Dear Readers:
As a nonprofit, we are dependent on the generosity of our readers.
Please consider making a small donation of any amount here. Thank you!
Fraught with controversy from the beginning, Keystone XL became a true political football during the Barack Obama presidency as the anti-oil and gas lobby in the U.S. mounted a disinformation campaign to kill public support for it. The mounting of the costly disinformation campaign made the process of obtaining permits at all levels of government – state, local, and federal – far more difficult and time-consuming, needlessly running up the project’s cost in the process.
After the Obama State Department led by Secretary John Kerry refused to issue the international cross-border permit required to complete the line, Trump quickly acted to ensure its approval early in his first term in office. By the time Joe Biden assumed office in January 2021, TC Energy had invested billions of dollars – creating thousands of high-paying jobs in the process – and well over half the line was already in the ground. Still, despite the huge sunk cost and lacking an ability to cite any instance in which TC Energy stood in violation of any U.S. law or regulation, Biden took the extraordinary, indefensible step of cancelling the project with the stroke of a pen.
But can the project really be revived now? It’s an important question given that Keystone XL was designed to bring as many as 830,000 barrels of Canadian oil per day into the United States for refining and delivery to markets.
Here, it is key to note that – as I pointed out last November when then-President-elect Trump raised this topic – TC Energy is no longer the owner of the moribund project. The remnants of Keystone XL were included in a group of assets TC Energy spun off last year when it formed a new company named South Bow Energy.
Complicating matters further is the fact that, after it decided the pipeline was a lost cause back in 2021, TC Energy pulled the installed pipe out of the ground so it could be repurposed for other projects in its portfolio. Then, there’s the fact that many of the permits the company spent years trying to obtain from various levels of governments are no longer valid and would have to go through the application and approval processes again were the project to be revived.
At the federal level, the Department of Interior and FERC would govern most of the necessary permitting processes. President Trump ordered all of his departments and commissions in January to research ways the executive branch can streamline the federal processes and Interior Secretary Doug Burgum included that goal as one of his 6 top priorities in a memo to staff dated February 3.
But even if those projects are successful in speeding up permitting at the federal level, they would have no impact on such challenges at the state and local levels. Activist groups who organized the opposition to the project saw great success in holding up permitting issuances at these lower levels of government, and would no doubt revive that strategy to attack any effort to restart the pipeline.
There can be no doubt that Trump’s desire to get the pipeline built is a laudable goal from a commercial, environmental and national security standpoint. Whether it is a practical goal is another question with many factors arrayed in opposition to it.
But one thing I’ve learned long ago is to never underestimate Donald Trump’s ability to get a deal done, so no one should give up hope just yet.
David Blackmon is an energy writer and consultant based in Texas. He spent 40 years in the oil and gas business, where he specialized in public policy and communications.
Alberta
Temporary Alberta grid limit unlikely to dampen data centre investment, analyst says

From the Canadian Energy Centre
By Cody Ciona
‘Alberta has never seen this level and volume of load connection requests’
Billions of investment in new data centres is still expected in Alberta despite the province’s electric system operator placing a temporary limit on new large-load grid connections, said Carson Kearl, lead data centre analyst for Enverus Intelligence Research.
Kearl cited NVIDIA CEO Jensen Huang’s estimate from earlier this year that building a one-gigawatt data centre costs between US$60 billion and US$80 billion.
That implies the Alberta Electric System Operator (AESO)’s 1.2 gigawatt temporary limit would still allow for up to C$130 billion of investment.
“It’s got the potential to be extremely impactful to the Alberta power sector and economy,” Kearl said.
Importantly, data centre operators can potentially get around the temporary limit by ‘bringing their own power’ rather than drawing electricity from the existing grid.
In Alberta’s deregulated electricity market – the only one in Canada – large energy consumers like data centres can build the power supply they need by entering project agreements directly with electricity producers.
According to the AESO, there are 30 proposed data centre projects across the province.
The total requested power load for these projects is more than 16 gigawatts, roughly four gigawatts more than Alberta’s demand record in January 2024 during a severe cold snap.
For comparison, Edmonton’s load is around 1.4 gigawatts, the AESO said.
“Alberta has never seen this level and volume of load connection requests,” CEO Aaron Engen said in a statement.
“Because connecting all large loads seeking access would impair grid reliability, we established a limit that preserves system integrity while enabling timely data centre development in Alberta.”
As data centre projects come to the province, so do jobs and other economic benefits.
“You have all of the construction staff associated; electricians, engineers, plumbers, and HVAC people for all the cooling tech that are continuously working on a multi-year time horizon. In the construction phase there’s a lot of spend, and that is just generally good for the ecosystem,” said Kearl.
Investment in local power infrastructure also has long-term job implications for maintenance and upgrades, he said.
“Alberta is a really exciting place when it comes to building data centers,” said Beacon AI CEO Josh Schertzer on a recent ARC Energy Ideas podcast.
“It has really great access to natural gas, it does have some excess grid capacity that can be used in the short term, it’s got a great workforce, and it’s very business-friendly.”
The unaltered reproduction of this content is free of charge with attribution to the Canadian Energy Centre.
Alberta
Alberta Next: Taxation

A new video from the Alberta Next panel looks at whether Alberta should stop relying on Ottawa to collect our provincial income taxes. Quebec already does it, and Alberta already collects corporate taxes directly. Doing the same for personal income taxes could mean better tax policy, thousands of new jobs, and less federal interference. But it would take time, cost money, and require building new systems from the ground up.
-
Business1 day ago
Carney government should apply lessons from 1990s in spending review
-
Business1 day ago
Trump to impose 30% tariff on EU, Mexico
-
Entertainment1 day ago
Study finds 99% of late-night TV guests in 2025 have been liberal
-
illegal immigration2 days ago
ICE raids California pot farm, uncovers illegal aliens and child labor
-
Frontier Centre for Public Policy18 hours ago
Canada’s New Border Bill Spies On You, Not The Bad Guys
-
Business6 hours ago
Mark Carney’s Fiscal Fantasy Will Bankrupt Canada
-
Energy1 day ago
LNG Export Marks Beginning Of Canadian Energy Independence
-
Uncategorized18 hours ago
CNN’s Shock Climate Polling Data Reinforces Trump’s Energy Agenda